Actionable news in PVG: PRETIUM RESOURCES Inc,

Pretivm Reports First Quarter 2016 Results

VANCOUVER, BRITISH COLUMBIA, May 12, 2016 (Marketwired via COMTEX) -- VANCOUVER, BRITISH COLUMBIA--(Marketwired - May 12, 2016) - Pretium Resources Inc. (PVG) PVG, -0.24% ("Pretivm" or the "Company") is pleased to report the following highlights from the first quarter of 2016 and updates for its high-grade gold Brucejack Project in northern British Columbia.

First Quarter 2016 Highlights

During the quarter the underground definition drill program continued to confirm the style and grade distribution of the Valley of the Kings gold mineralization and continued to intersect high grade and visible gold (see news releases dated January 12, 2016 and March 8, 2016).

On February 17, 2016, we announced an updated cost and working capital estimate for the Brucejack Project. The estimated total project capital cost to complete design, construction, installation and commissioning, including contingencies and working capital, is US$696.8 million.

On March 1, 2016, we closed a marketed offering of 28,384,000 common shares at a price of US$4.58 per common share for gross proceeds of US$130 million. Subsequent to the close of the marketed offering, certain holders exercised their participation rights to maintain their proportionate ownership interest in the Company. The total number of common shares issued in connection with the marketed offering and private placement was 31,923,755 for aggregate gross proceeds of approximately US$146.2 million.

Working capital at March 31, 2016 was $455.8 million.

Subsequent to the end of the quarter, on April 18, 2016, we reported on the progress of site construction activities at the Brucejack Project including the camp, mill site, portal excavation and transmission line. Construction and underground development remains on-schedule and on-budget for commissioning of the underground mine in mid-2017.

On April 5, April 26 and on May 12, 2016, we announced additional results from the underground infill program at the Brucejack Project's Valley of the Kings. Results continue to demonstrate high-grade gold mineralization, including hole VU-722 which intersected 37,117 grams of gold per tonne uncut over 0.50 meters.

Advancing the Brucejack Project - Construction Progress

The foundation for the 330-person camp at Brucejack is complete and the installation of prefabricated modules for the camp is underway. The camp is expected to be operational early in the third quarter of this year.

Excavation to level the site for the mill facility has been completed, and concrete works are well underway. The structural steel installation for the mill building is scheduled to begin in June, with full enclosure of the mill building expected in the third quarter. Installation of internal structural steel and mechanical equipment will commence prior to full enclosure.

Surface excavation for the Valley of the Kings portal pad advanced during the quarter. The portal will serve as the primary access point to convey the gold ore from the underground crusher to the mill.

Underground development remains on schedule and crews are advancing at a rate of over 20 meters a day. Current underground activity at the Valley of the Kings includes excavation of the 1260-meter level ramp, development of the 1320-meter level, installation of ladderways and platforms in the fresh air raise and the excavation of headings for infrastructure.

The transmission line towers have begun arriving at site from the fabricator and installation will be ongoing throughout the second and third quarters, with connection to the BC Hydro power grid expected in the fourth quarter.

Project Engineering and Procurement

Detailed project engineering is ongoing. All long lead-time items have been ordered, including the ball and SAG mills which are scheduled to arrive on site in the third quarter.

Project Financing

On September 21, 2015, we completed a US$540 million construction...